Projects

Our Projects

HIRING OF SERVICES FOR 2D-3D STRUCTURAL GEOLOGICAL MODELING STUDY OF THE GURGALOT BLOCK
-HIRING OF 2D SEISMIC DATA PROCESSING SERVICES FOR PALANTAK AND SHAHANA E.L ‘s UPTO PRE-STACK TIME MIGRATION
-Kharan Basin 2D/3D Seismic Survey
-Kharan Basin Gravity & Magnetic Seismic Surveys
-Kharan Basin scouting report conducted
– HIRING OF 2D SEISMIC Surveys for PALANTAK AND SHAHANA E.L
-Hiring of 3D Seismic Survey in Garhi Area Fatehjang E.L


-Performed services to supply imported sub bituminous coal to FFBL, FFC, Coal Power Plants at Bin Qasim and Sahiwal.
-Performed successful consultancy with CCCC for Havelian-Thakot Project of National highway Authoirty

1- CSCEC – PKM Project
a. Multan – Sukkur Section (M-5)
2- DGDP (Army, Navy, Air Force)
3- FWO Projects
a. M-9 – Karachi Hyderabad Motorway
c. Water Supply Project

5- Coal Project Consultancy
b. SECMC – Sindh Engro Coal Mining Company to perform seismic activities
6- Gharo Solar Power Project consultancy
8- Metro Bus System Project Consultancy
9- NLC Projects, Central Punjab
10- Bahria Town Projects, Karachi
11- DHA Projects, Karachi & Lahore
12- AFOHS Projects, Karachi
13- NHS Projects, Karachi & Gharo
16- SMDERI – PQA Project
17- SEPCO 111 – PQA Project
18- Ssangyong Usmani JV – KPT Project
19- CHEC – PQA project
18- CEEC – Energy China (Power Cement Project, Jamshoro, Sind)
19- Pioneer Cement (Hydro Project & Extension, Khushab, Punjab)

...............................

Sr. No

Name of Project

Date of Completion

 

                                                                                          220 kV Grid Stations

1

220 kV Mansehra Grid Station

10-02-2018

 

2

220kV Chakdara Substation (2×250 MVA)

16-09-2018

 

3

220kV D.I Khan Substation (2x250MVA)

18-02-2019

 

                                                                                     220 kV Transmission Lines

4

Chashma-Bannu 220 kV T/Line (126 km)

11-10-2016

 

5

220kV T/L for Mansehra Grid Station (1 km)

16-11-2017

 

6

220kV T/L for Chakdara Grid Station (70 km)

16-09-2018

 

7

Reconductoring of 220kV Tarbela – Burhan D/C T/Line Circuit 1&2

28-02-2019

 

                                                                                   132 kV Transmission Lines

8

17 MW Ranolia HPP 132kV T/Line (1.5 km)

08-05-2017

 

Chashma-Bannu 220 kV T/Line (126 km)

11-10-2016

 

9

220kV T/L for Mansehra Grid Station (1 km)

16-11-2017

 

10

220kV T/L for Chakdara Grid Station (70 km)

16-09-2018